On Friday, April 4, 2008 at 12:40:52 AM UTC+8, Ron Coderre wrote:
You're very welcome.
Regards,
Ron
Microsoft MVP (Excel)
"hurds999" <[email protected]> wrote in message news:[email protected]...
Thank you both very very much. The formula(s) worked!! You're both very awesome!!! Have a great Wednesday, because you've made mine!!! =)
"Ron Coderre" wrote:
If you have the Analysis ToolPak add-in installed:
A2: =EOMONTH(A1,0)+1
If you don't....
A2: =DATE(YEAR(A1),MONTH(A1)+1,0)+1
Does that help?
Post back if you have more questions.
--------------------------
Regards,
Ron
Microsoft MVP (Excel)
(XL2003, Win XP)
"hurds999" <[email protected]> wrote in message
news:[email protected]...
I have a date in A1, but I need to populate A2 with the first day of the >> > following month. Example: A1 = 05/17/08, A2=06/01/08
What formula would best work to accomplish this? I'm guessing this
would
be
easy, but I can't get anything to work.
Thank you in advance for any assistance.
Hi! I have an almost similar question to this. How can I round up the date in Cell A3 to the nearest weekday? I hope to hear from you. Thank you so much!